§ 22-194. Operation, maintenance of pretreatment or flow-equalizing facilities.  


Latest version.
  • (a)

    Industrial users shall provide wastewater treatment as necessary to comply with this article and shall achieve compliance with all categorical pretreatment standards, local limits, and the prohibitions set out in sections 22-188—22-191 of this article within the time limitations specified by EPA, the state, or the city manager, whichever is more stringent. Any facilities necessary for compliance shall be provided, operated, and maintained at the user's expense. Detailed plans describing such facilities and operating procedures shall be submitted to the city manager for review, and shall be acceptable to the city manager before such facilities are constructed. The review of such plans and operating procedures shall in no way relieve the user from the responsibility of modifying such facilities as necessary to produce a discharge acceptable to the city under the provisions of this article.

    (b)

    Upon reduction of efficiency of operation, or loss or failure of all or part of the treatment facility, the permittee shall, to the extent necessary to maintain compliance with its permit, control its production or discharges (or both) until operation of the treatment facility is restored or an alternative method of treatment is provided. This requirement applies, for example, when the primary source of power of the treatment facility fails or is reduced. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit.

    (c)

    A user may allow any bypass to occur which does not cause pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation. These bypasses are not subject to the provisions of paragraphs (d) and (e) of this section.

    (d)

    (1) If a user knows in advance of the need for a bypass, it shall submit prior notice to the city, at least ten days before the date of the bypass, if possible.

    (2)

    A user shall submit oral notice to the city of an unanticipated bypass that exceeds applicable pretreatment standards immediately upon it becoming aware of the bypass. A written submission shall also be provided within five days of the time the user becomes aware of the bypass. The written submission shall contain a description of the bypass and its cause; the duration of the bypass, including exact dates and times, and, if the bypass has not been corrected, the anticipated time it is expected to continue; and steps taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass.

    (e)

    (1) Bypass is prohibited, and the city may take enforcement action against a user for a bypass, unless:

    a.

    Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage;

    b.

    There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and

    c.

    The user submitted notices as required under subsection (d) of this section.

    (2)

    The city manager may approve an anticipated bypass, after considering its adverse effects, if the city manager determines that it will meet the three conditions listed in subsection (e)(1) of this section.

(Ord. No. 96-7-2, 7-22-96)